Completed Assignments -Samples
1- Project Management (Planning)
2010-2012 Planning and Scheduling for Al- Mussafah-Abu Dhabi Supply Project. Location- Abu Dhabi International contracting Company (Aydiner)
2008 Evaluating and assessing delays in Boulevard Al-Abdali Project (Assessment of project Time) (Amman) CC consultant
2006 Service Contract: Developing and Updating work schedule of Greater Amman Water Sector Improvement Program. EU funded Al-Meyyah Project
2- Setting up PPP and PSP Projects
2010-2012 Our team members represented the Owner in concluding the PPP (BOT) contract of Expanding As Samra WWTP MWI
2010 Our team members represented the Owner in concluding the Management Contract of Northern Governorate Water Administrations (Yarmouk Water Company) NGWA
2009-2010 Our team members represented the Owner in concluding the different PSP initiatives including outsourcing of the billing and collection of water services in three governorates (three contracts) –Madaba, Karak and Balqa. The contract were incentive based contracts. WAJ
2009-2012 Our team members also lead the efforts to develop performance based energy saving contracts in the water sector (feasibility studies, contracting of pumping station and WWTP)
3- Performance Monitoring
2016-2017 Assessment and evaluation of the Indicators of the 3rd Arab State of the Water Report-2015- Jordan